Rinnai 26 RHFE-750ETR Flue Installation Manual
Ground excavation is not recommended to meet clearance or space requirements unless
there is sufficient drainage provision.
d.) Mark the centre of the heater flue pipe on the rear
wall (see photo).
e.) Using the mounting brackets supplied, mount the
‘On Wall’ kit with so that the centre of the flue
pipes aligns with the markings on the wall using
the stand off clips supplied. The condensate trap
should be pointing towards the floor.
Mark centre of hole through floor directly beneath
centre of condensate trap. Cut 100 mm dia. hole
through floor.
In ‘Down and Out’ applications only, the ‘up’ marking on the condensate trap will point
‘down’. This is normal. In a ‘Down and Out’ application, the positioning and direction of the
condensate trap do not matter as no condensate will be collected & drained. Condensate
drainage is ensured by the two degree ‘fall’ towards the terminal.
Condensate trap must still be fitted.
f.) Fit 2 x 45° bends (ESBEND) together and fit the
resulting bend assembly to the ‘free’ (non
socketed) end of a Co-axial flue pipe
(ESPIPE900) - see photo.
g.) Mount the ESPIPE900 and bends temporarily in
the horizontal plane beneath the floor, using the
stand off clip for correct spacing under bearers
etc. so that the free end of the bend assembly
faces vertically up towards the condensate trap
(see photo).
A small amount of ‘O’ ring lubricant on rubber seals will assist assembly.
h.) Measure the vertical distance ‘Y’ between the free
end of the ESBEND’s and the condensate trap.
This distance will be used to cut a Co-axial pipe
(ESPIPE900) to the correct length to join
between the free end of the ESBEND and
condensate trap - see photo.
i.) Cut an ESPIPE900 to length as follows:
Length of outer pipe is distance ‘Y’ plus 60 mm to
allow for connection penetration to mating part.
Ensure the inner pipe extends 12 mm past the
outer pipe - (‘Y’ plus 72).
NOTE
378m
567mm
+/-
25mm
Floor level
Centre line of
appliance
Centre flue connection
to align with centre
mark on wall
NOTE
bend
assembly
bend
assembly
free end
NOTE
12mm
‘Y’+ 60mm
‘Y’+ 72mm
‘Y’
DOWN & OUT FLUE INSTALLATION